Introducing Remaining Effort
Project managers can specify the planned effort for each assignee of a project task. The actual effort increases every time an assignee enters a value in the Time spent field of the project task. 4me then used the actual effort and the planned effort values to determine the task’s progress.
This used to be calculated as follows:
progress = actual effort / planned effort
But when an assignee sees that it is going to take significantly longer to complete a project task than originally planned, this could not be reflected in the progress bar of the task. To make this possible, the assignees now have the ability to specify the amount of time they still expect to spend on the task in the new Remaining effort field.
The value in the Remaining effort field of each assignee is now used to calculate the progress of a project task as follows:
progress = actual effort / (actual effort + remaining effort)
It is important to note that only the time entries and remaining effort of internal people are considered for the progress calculations. Internal people are defined here as the people who are registered in the 4me account in which the project is registered or its directory account. The project manager is not allowed to see the time spent by people who are registered in another 4me account (e.g. the account of an external provider).